Recent Progress of 5 small hydro power plants renovation

Ubol Ratana Dam           

Up to the end of January 2010, Ubol Ratana Renovation Unit 1-3 work progress is 24.16%. The LOI for Ubol Ratana Hydro Power Plant Units 1-3 was awarded on December 25, 2009. The equipment is now in under manufacturing.

Picture of Progress

Installation of Cable Tray for power cable of excitation in Generator Pit

Excavation of 115 KV Disconnecting switch to the new platform

   

 

 

 

 
 
 