Project for Hydropower Development at Irrigation Dams

Mae Klong Hydro Power Plant           

The LOI (Letter of Intent) was released on September 15, 2008.  Kick off meeting on December 22, 2008. At the end of December 2008, the construction progress of the new RID’s office building is now 35%.

Picture of Progress

The construction of new building for the RID’s office administration & maintenance work progress is 58%

   

The new RID’s savings Cooperative building (Mae Klong) construction work progress is 53%.

 

 

The new RID’s Office 2 Regional Irrigation 13 construction work progress is 57%.

 

The fence construction work progress is 83%.

 
 

 