Recent Progress of 5 small hydro power plants renovation |
Kaeng Krachan Dam |
Up to the end of January 2010, Kaeng Krachan Renovation Unit 1 work progress is 87.83%. |
| Picture of Progress |
 |
Head Cover & Runner Installation in Pit : December 15, 2009 |
| |
|

|
Rotor Lifting Installation in Pit : January 12, 2010 |
| |
|
 |
| Inlet Valve Installation : January 19, 2010 |
|
|
|